- the progress is reported obligatory every 6 months through the
Project implementation report
,
which is completed by the group research leader, i.e. the deadline is the last day of April and October, repeatedly every year
- the Report is send by an email to the OP VVV office lenka.sterbova@uochb.cas.cz
- in the meantime, the OP VVV office organises regular meetings, which take place every 6 months (July and January), with the following content:
- summary of the activities scheduled for the previous 6 months
(Lenka Štěrbová)
- progress reported by the individual research teams – whether the objectives have been achieved
- summary of the activities planned for the following 6 months
(Lenka Štěrbová)
- separate meetings for each one of the three research programmes