• the progress is reported obligatory every 6 months through the Project implementation report  , which is completed by the group research leader, i.e. the deadline is the last day of April and October, repeatedly every year
  • the Report is send by an email to the OP VVV office lenka.sterbova@uochb.cas.cz
  • in the meantime, the OP VVV office organises regular meetings, which take place every 6 months (July and January), with the following content:
    1. summary of the activities scheduled for the previous 6 months (Lenka Štěrbová)
    2. progress reported by the individual research teams – whether the objectives have been achieved
    3. summary of the activities planned for the following 6 months (Lenka Štěrbová)
  • separate meetings for each one of the three research programmes